Consent to Establish (CTE)

Environmental Clearance for New Industrial Projects

What is Consent to Establish (CTE)?

Consent to Establish (CTE) is a mandatory environmental clearance required before setting up a new industrial unit, expanding an existing facility, or undertaking any activity that may generate pollution. It is issued by the State Pollution Control Board (SPCB) or the Central Pollution Control Board (CPCB), depending on the nature and scale of the project.

CTE is governed by the Water (Prevention and Control of Pollution) Act, 1974, and the Air (Prevention and Control of Pollution) Act, 1981. It ensures that the proposed project complies with environmental norms and has adequate pollution control measures in place before construction or installation begins.

Consent to Establish is the first step in environmental compliance for industries. After establishment, industries must obtain Consent to Operate (CTO) to commence production or operations.

Who Needs CTE?

CTE is required for:

New Industrial Units

Any new manufacturing, processing, or industrial facility that is likely to generate air emissions, wastewater, hazardous waste, or solid waste.

Expansion of Existing Units

Expansion, modernization, or diversification of existing facilities that may increase pollution load.

Polluting Activities

Activities that involve discharge of effluents into water bodies or emissions into the atmosphere.

Industries Covered

• Chemical and pharmaceutical plants

• Textile and dyeing units

• Food processing industries

• Power plants and thermal units

• Mining and mineral processing

• Cement and construction material plants

• Pulp and paper mills

• Metal and metallurgical industries

Key Requirements for CTE

Pollution Control Measures

The applicant must provide detailed plans for pollution control, including:

  • • Effluent Treatment Plant (ETP) for wastewater
  • • Air Pollution Control Devices (APCDs) like scrubbers, filters, ESPs
  • • Solid and hazardous waste management systems
  • • Noise pollution control measures

Environmental Impact Assessment (EIA)

For large or highly polluting projects, an EIA report may be required to assess potential environmental impacts.

Compliance with Standards

The proposed facility must meet emission and effluent discharge standards prescribed under the Water and Air Acts.

Site Suitability

The location must be in compliance with zoning regulations, and not in ecologically sensitive areas unless permitted.

CTE vs CTO

AspectConsent to Establish (CTE)Consent to Operate (CTO)
PurposeFor setting up/establishing a new unit or expansionFor operating or running the established unit
When RequiredBefore construction/installation beginsAfter construction, before starting production
ValidityTypically valid until the project is completedRenewable periodically (1-5 years depending on category)
FocusDesign and pollution control infrastructureActual pollution generation and compliance monitoring

Benefits of Obtaining CTE

Legal Compliance

Avoids penalties, legal action, and project shutdowns for operating without consent.

Smooth Project Setup

Facilitates uninterrupted construction and installation activities.

Environmental Protection

Ensures pollution control measures are integrated from the design stage.

Easier CTO Approval

Having CTE in place streamlines the process of obtaining Consent to Operate later.

Investor Confidence

Demonstrates regulatory compliance, enhancing credibility with investors and lenders.

Access to Incentives

Eligibility for government subsidies, grants, and environmental certifications.

CTE Application Process

1

Prepare Project Report

Develop a detailed project report including pollution control plans, effluent/emission details, and waste management strategy.

2

Submit Application

File application with the SPCB/CPCB along with required documents, site plan, and consent fees.

3

Site Inspection

SPCB officials conduct site inspection to verify details and assess environmental feasibility.

4

Review and Approval

SPCB reviews the application, project report, and inspection findings. May request additional information or modifications.

5

Grant of CTE

Upon satisfactory review, SPCB issues Consent to Establish with specific conditions and timelines.

6

Compliance and CTO

After construction completion, apply for Consent to Operate (CTO) to begin production.

Request Consultation

Fill out the form below and our experts will get back to you within 24 hours.

Upload relevant documents (PDF, JPG, PNG, DOC, XLS). Max 5 files, 10MB each.

Click to upload or drag and drop

PDF, JPG, PNG, DOC, XLS (Max 10MB)